Milestones

Land Purchased: February, 2011

Closing of Property: July, 2011

Committee of Adjustment to apply for Laneway Ownership: April, 2012

Blueprints Completed: December, 2012

City of Mississauga Site Plan Application: January, 2013

Site Plan Approval: June, 2013

Region of Peel Approval: August, 2013

Over-consumption of Moet: August 21, 2013 (Building Permit Issued!!!!!!!!!!!!)

Demolition: September, 18, 2013

 

 

 